River Cell Repair

       
   Damaged Cells were cracked and losing ballast material.                                  Steel sheets were rolled to cell diameter                 

        
  Sheets were welded together and drilled to create bands.                         Flat stock was fitted with brackets to bolt together.        

        
These sheets were welding together onsite before being loaded onto our barge and installed on the cells.

            
Our crane was driven on our barges.                                              Bands were positioned into place using the crane.  


Divers placed the bands and fastened them together.

New Hydro Installation in Water Control Tower

         

           

                       


              
Cofferdam Fabrication & Installation, Debris Removal  

    

    
 
    